Manufacturing of torrefied pellets without a binder from different raw wood materials in the pilot plant

This paper concentrated on the production of torrefied without an additional binder from different raw wood materials. The torrefaction and pelletizing was carried out at the Torrec Ltd. pilot plant located in Eastern Finland and its effective capacity was 2,200 tonnes per year. Six different woodchips lots were tested in the pilot runs. The test was to identify whether the pelletizing process requires an additional sealant as a binder. The pelletizing process only exploited condensation water that came about from the torrefaction process. The temperature control range and the holding time were varied, regarding the driving parameters. Finally, quality factors were analysed from torrefied pellets and its raw wood materials after each pilot run. The maximum temperature of the reactor, 260°C, was perhaps too low to manufacture pellets of high energy content. Based on the study, the pelletizing process will not require an additional binder in the future.